Sixty North Gold Provides Project Update on Winter Road to Mon Gold Mine
16 January 2026
Sixty North Gold Mining Ltd (the "Company" or "Sixty North Gold") is pleased to provide an update on its plan to commence gold production this year on its wholly-owned Mon Gold Mine, Yellowknife, NWT.
Sixty North Gold has been informed that construction of the southern half of our winter road has commenced from Highway 4, 20 km east of Yellowknife, northwards across Prosperous Lake for a total extent of approximately 15 km. The balance of the road to the Mon Gold Mine site (approximately 30 km farther north) will be installed and managed by Matrix (https://matrixco.ca/) commencing next month. A total of 19 truckloads of supplies including the 100 tpd mill will be hauled to site in February and March.