Update on the Kennady North winter drilling program
20 March 2018
Kennady Diamonds Inc. is pleased to provide an update on the winter drilling program at the Kennady North Project. Drilling is proceeding well with a total of 1,868 meters of drilling completed to date. Included in today’s release are three exploration/delineation holes and one geotechnical hole completed on the Faraday 1-3 kimberlite, and two delineation holes completed on Faraday 2. All eleven drill holes completed on the program to date have intersected kimberlite.
In addition to the geotech drilling completed to date on Faraday 1-3, a number of delineation/exploration holes have been drilled in the area between the two limbs of the kimberlite complex.
Approximately 10,500 meters of diamond drilling is planned for the 2018 winter program, with 40% assigned to delineation and geotechnical drilling of the Faraday bodies, and 60% dedicated to testing high-priority grassroots exploration targets within the Kelvin-Faraday Corridor. Exploration drilling on the high-priority targets will commence when drilling on the Faraday 1-3 kimberlite is completed.