Update on the Kennady North winter drilling program

7 March 2018

Kennady Diamonds Inc. is pleased to provide an update on the winter drilling program on the Kennady North Project. Winter infrastructure is now in place and two core rigs are fully operational with a total of 990 meters of drilling completed to date. Included in these initial results are two geotechnical holes and three exploration/delineation holes completed on the Faraday 1-3 kimberlite, with all five holes intersecting kimberlite.
The drilling at Faraday 2 will also collect geotechnical as well as environmental data relevant to open pit and underground mine modeling. 
Approximately 10,500 meters of diamond drilling is planned for the 2018 winter program, with 40% assigned to delineation and geotechnical drilling of the Faraday bodies, and 60% dedicated to testing high-priority grassroots exploration targets within the Kelvin-Faraday Corridor.