Mountain Province Updates Gahcho Kué Diamond Mine Development

14 March 2016

?     Overall project more than 87 percent complete
?     On plan for first production in H2 2016
?     Appointment of Mine General Manager
 
Toronto and New York, March 14, 2016 – Mountain Province Diamonds Inc. (“Mountain Province”, the “Company”) (TSX: MPV, NASDAQ: MDM) is pleased to announce that development of the Gahcho Kué diamond mine is progressing according to plan with the overall project more than 87 percent complete and on track for first production during H2 2016. 
 
Patrick Evans, Mountain Province President and CEO, commented: “We continue to make excellent progress at Gahcho Kué. Key areas of focus are remaining earthworks, commissioning of the primary crusher and diamond plant, pre-stripping and stockpiling of kimberlite as well as preparations for operational readiness.”
 
Mountain Province is also pleased to announce that the Gahcho Kue Joint Venture has appointed Allan Rodel as the mine general manager. Mr. Rodel joined the De Beers Group in 1997 and has held a number of senior management positions, including that of Gahcho Kue project manager since 2013. Mr. Rodel has an honors degree in chemical engineering from the University of Natal and resides in Yellowknife, N.T.
 
In addition to Mr. Rodel, nine senior operational appointments have been made at Gahcho Kue, including the mining manager, engineering and maintenance manager, ore processing manager and technical services manager. Under the leadership of Mr. Rodel and the operations management team, commissioning of the Gahcho Kue mine is well underway.
 
Mr. Evans added: “We are also pleased to report that the ice road deliveries to Gahcho Kue are proceeding to plan. Importantly, delivery of critical large mining equipment to site was completed last week with the bulk of the remaining deliveries being diesel fuel. The project also continues to meet our lending group’s tests-to-completion with US$73M advanced to fund cash calls during Q1 2016. A total of US$231M has been drawn against the US$370M facility. An update on performance against budget will be provided with the yearend results at the end of March.”